The tube is U-shaped and was pressure tested before they inserted it in to the well. On site, I believe they had to fill the tube with water before they could sink it in to the hole.
The big surprise to me was the thermal grout. The thermal grout is supposed to help the tubes make a good thermal connection with the ground. They used a substance called Therm-Ex. It is supposed to remain soft and flexible so that the tubes can expand and contract as they change temperature. Some how I imagined (incorrectly) that it would be more like a rigid cement.
Tomorrow the third and final outside crew comes to excavate a trench 4-feet down between the holes and then on to the foundation. They'll bore 2 holes in to the foundation. The two U-pipes will be connected in parallel and the connecting pipes will get inserted in to the basement. They run the pipes 4-feet down to use the ground as insulation for the water in the tubes.